Sample Questions
Q) You use a planning time fence and fixing type 1. You receive a customer order with a material availability date within the planning time fence. What do you have to consider in this scenario?
a) Planned orders that are created by requirements planning are shifted to the end of the planning time fence.
b) Requirements planning considers only changes that are relevant for scheduling within the planning time fence.
c) The MRP controller cannot create planned orders within the planning time fence.
d) Planned orders are created within the planning time fence and automatically firmed by requirements planning
Q) Which Customizing element controls the determination of planned costs in production orders?
a) Costing variant
b) Calculation procedure
c) Settlement profile
d) Accounting type
Q) Which issue can occur if the lot size-dependent in-house production time in the material master is not updated after changing the routing?
a) Lead time scheduling cannot take place.
b) Requirements planning creates an appropriate exception message in basic dates scheduling.
c) Subsequent capacity planning is no longer possible due to the obsolete scheduling parameters.
d) Dependent requirements request the components from the bill of materials at wrong times when using basic dates scheduling.
Q) Where in the SAP ECC system can you define production versions?
a) In the bill of material
b) In the work center
c) In the material master
d) In the routing
Q) When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula parameters for calculation. What can be the origin of the formula parameters used for scheduling? (Choose three)
a) Standard values in the operations of routings
b) General operation values of routings
c) General values from work scheduling view of the material master
d) User-defined fields in the operation of routings