Sample Questions
Q) The stakeholder register is an output of:
a) Identify Stakeholders.
b) Plan Stakeholder Management.
c) Control Stakeholder Engagement.
d) Manage Stakeholder Engagement.
Q) An output of the Develop Project Team process is:
a) change requests
b) team performance assessments
c) project staff assignments
d) project documents updates
Q) Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?
a) Portfolio
b) Project
c) Program
d) Operations
Q) Which type of manager is assigned by the performing organization to lead the team that is responsible for achieving the project objectives?
a) Program
b) Functional
c) Project
d) Portfolio