Sample Questions
Q) risk response strategies, in which the project team moves the impact of a threat, along with ownership of the third-party response, called:
a) soften
b) take
c) transfer
d) to avoid
e) None
Q) What type of relationship is set based on the knowledge of best practices in a specific field of application, or some unusual aspect of the project, in which it is desirable to sequence-specific, although there may be other acceptable sequences?
a) external
b) interior
c) compulsory
d) discretionary
e) None
Q) While the processes in the planning group seeking to team feedback and determine the project documents for the project work management, organizational procedures dictate when the project planning
a) ends
b) begins
c) delay
d) rejected
e) None
Q) When painting the bedroom, wall preparation can be done while the paint is selected. This is an example of a:
a) lead
b) lag
c) mandatory dependency
d) internal relationship